Lycopodium provided the Engineering, Procurement and Construction Management (EPCM) services for the expansion of the mine, which included a new milling circuit with 1.19 Mtpa capacity and an expansion of the CIP circuit to increase tonnage from 1.36 to 2.46 Mtpa.
Construction and commissioning was completed in December 2022 and Lycopodium has subsequently commenced work on the mine’s new primary crushing plant.