Having previously completed the project’s Feasibility Study in 2018, in 2019 Lycopodium delivered a study update looking at further optimisation of the Boto plant and infrastructure to advance the engineering of the Boto plant with a revised throughput of 2.7 Mtpa.
In 2020 Lycopodium was awarded the first phase of an Engineering and Procurement (EP) scope, which included access road and air strip detailed design and tendering to the construction contractors, as well as progressing the permanent camp and process plant designs with major vendor certified data. An early works package was awarded in 2021, including a road to provide permanent access to the site and engineering for critical plant equipment.
In April 2023, Managem Group purchased Boto from IAMGOLD, and subsequently proceeded to restart the project. Lycopodium undertook a review of the overall process plant design, changing the milling strategy from a single stage semi-autogenous grinding (SAG) mill to a SAG and Ball Mill Combination (SABC).
Lycopodium is now delivering the Engineering, Procurement and Construction Management (EPCM) scope for the project. First gold is anticipated Q2 2025.